Parts of Monomoy and Shimmo are on a low-pressure sewer line. A listing that says "town sewer" there can mean the house sends its wastewater through a pump on the lot. Nantucket's sewer regulations, Chapter 336, section 5H, address grinder pump operation and maintenance.
Most buyers file "sewer" with water and electricity, as a service the town provides. In this part of the north shore, a low-pressure line relies on a piece of equipment on the property, more like the boiler or the generator. The pump is easy to overlook on a $19.5 million closing, but it still needs a check during due diligence.
A sewer extension built mostly on low-pressure line
Monomoy and Shimmo sit along the harbor east of Town. The Town's sewer operations manual describes the Nantucket Harbor Shimmo and Plus Parcels Sewer Extension as nearing completion in March 2019, serving properties through both gravity and low-pressure sewer. The project added 9,000 linear feet of new gravity sewer and 31,000 linear feet of new low-pressure sewer, along with a new pump station on Wamasquid Drive, and an upgraded Monomoy South Pump Station to handle the extra flow. An earlier Town planning sheet for the Shimmo Infrastructure Expansion gave somewhat different numbers: 185 connections, 26,500 linear feet of low-pressure sewer, and an estimated cost of $16.7 million, connecting to the Surfside treatment plant "via Monomoy Infrastructure."
A low-pressure line needs something at each house to push the wastewater into it. That job falls to a grinder pump in a tank on the property. According to the Town's operations manual, the construction contract supplied the grinder pumps to homeowners. The manual also says that, "as is the standard policy on the island," the Nantucket Sewer Department does not own, operate, or maintain grinder pumps on private property.
The pumps installed around 2019 have now been running for years.
What the Town has said about pumps that fail
These questions came up recently, though for a different neighborhood. In 2026 voters approved the Somerset Needs Area sewer extension, and Town Meeting removed the proposed betterment fees on affected property owners, Nantucket Current reported. Somerset residents asked about grinder pumps, and a project FAQ marked as a September 2026 draft for Town review answered with Shimmo and Monomoy as the examples.
| Question | What the draft 2026 FAQ says |
|---|---|
| Have pumps failed here? | The Sewer Department reports "a limited number of failures" in existing installations, "including areas of Shimmo and Monomoy." |
| What happened to them? | Pumps that failed under warranty were replaced. |
| What causes problems? | Grease, wipes, excessive sand and paint. |
| What about a power outage? | The pump needs electricity. Town staff estimate its tank stores about 48 hours of wastewater, depending on household water use. |
| Can backup power help? | A properly configured generator can power the pump. |
Two of those answers matter most in Monomoy. A pump that has been running since the Shimmo project went in may no longer be covered by a warranty. The 48-hour estimate depends on use. A full house over a holiday weekend fills the tank faster than one person in the off-season. The FAQ's advice during an outage is to cut back on water use until power returns. Whether the generator is wired to the pump circuit is a simple question to ask during due diligence.
Sewer and septic in Monomoy
Not every Monomoy or Shimmo house is on the low-pressure line. Some use gravity sewer, and some may still run on a septic system.
The Town's sewer permit packet, revised August 24, 2026, lists a residential new-connection permit at $1 per square foot with a $4,000 minimum, and $300 for disconnect, reconnect and repair permits. The same packet includes a capacity fee schedule dated June 2020 that rises each year with inflation, so its printed amounts are not current. Ask the Sewer Department for this year's figure.
What to ask before an offer goes in
Monomoy prices put all of this in context. In the transfer period of September 10 to 17, 2026, Nantucket Current's real estate roundup recorded 69 Monomoy Road selling for $19.5 million. The sale carried a $390,000 Land Bank fee against an assessed value of $8,260,300. At that price, a pump replacement is a small line item. The bigger risk is finding out about it during an outage on a full summer weekend. These are questions to ask:
- Which system serves the house? It may be gravity sewer, low-pressure sewer with a grinder pump, or septic. The Nantucket Sewer Department can confirm for a specific property, and the answer shapes the rest of the list.
- If there is a pump, how old is it and what records exist? Ask for the install date, model, service history and any warranty paperwork.
- What powers the pump during an outage? Check whether a generator is wired to it.
This post is general information about Town rules. It is not legal, engineering or financial advice. Please confirm pump ownership and maintenance obligations for a specific property with the Nantucket Sewer Department or your own attorney, and its wastewater system with the Board of Health or your inspector.