The new shared-use paths on Lovers Lane and Monohansett Road are now paved. Since work restarted in September, the shoulders have been loamed and seeded. More than 150 trees and 250 native shrubs are going in along Lovers Lane to soften what the Town calls "months of heavy construction." Final paving on both roads, including Cape Cod berms, is expected in November, and the Town's goal is to finish before the holidays.
That covers two of the three roads in the Surfside Area Transportation Improvements Project. The third is Okorwaw Avenue, which joins the other two, and it hasn't been started. Until it is built, the two new paths stay as separate pieces.
Okorwaw Avenue is the piece that joins the other two
The Town defines the project as three segments:
- Lovers Lane, from Old South Road to the Boulevarde
- Okorwaw Avenue, from Lovers Lane to Monohansett Road
- Monohansett Road, from Okorwaw Avenue to Miller Lane
Okorwaw is the short road in the middle. The Town's September newsletter calls the path planned along it "the Lovers Lane–to–Monohansett bike path." The project's stated purpose is to fill a gap between paths that already exist. The Town says it "provides a much-needed connection between the existing shared-use paths on Airport Road, Old South Road, and the Boulevarde."
When all three roads are done, the area gets about 2.4 miles of new bike paths, according to the Select Board update reported by The Inquirer and Mirror in October 2025. The same update said the Okorwaw Avenue and Monohansett Road intersection will become a four-way stop.
The October 2025 plan and where each road stands now
Last fall, the Town gave the Select Board a road-by-road schedule. Here is that plan next to what the Town has since reported.
| Segment | Planned window, per the Oct. 2025 update | Status in Town reports through Nov. 3, 2026 |
|---|---|---|
| Lovers Lane, north | September–December 2025 | Drainage done and first layer of pavement down by late May 2026. Path paved this fall. Final paving expected in November |
| Lovers Lane, south | December 2025–January 2026 | Same as above |
| Monohansett Road | January–May 2026 | Drainage done and first layer of pavement down by late May 2026. Path paved this fall. Final paving expected in November |
| Okorwaw Avenue | May–December 2026 | On hold until utility lines are moved |
| Punch list and cleanup | Spring 2027 | Completion still targeted before summer 2027 |
Lovers Lane and Monohansett have gone roughly to plan. In May, the Town reported that drainage was complete on both roads and on nearby side streets, with the first layer of pavement down. Crews then spent about four weeks on driveway transitions, pavement markings, signage and cleanup so the roads would be ready for summer. Okorwaw was supposed to be built across the second half of 2026. Instead, it is the work that carries into the next construction window.
Why Okorwaw is waiting on the utility companies
The October/November Town Manager Newsletter explains the delay:
"Work on Okorwaw Avenue is still on hold. Utility companies need to finish moving their lines first, so there's room for new drainage, the realigned road, and the bike path."
Okorwaw is being rebuilt as a realigned road with new drainage and a path, and all three need space that the existing utility lines currently occupy. In September, the Town said the same order applied: once the utility relocations were finished, crews would move on to drainage, roadway reconstruction and the path.
The calendar matters here. Construction is permitted between Labor Day and Memorial Day each year. The Town can allow work after Memorial Day if the contractor asks, depending on the type and location of the work. In May, the Town said the project was on schedule to finish "well before summer 2027." That leaves this winter and spring to build Okorwaw and its connecting path.
What's already been built besides the paths
Several smaller pieces of the project are already in place, and they show what the finished corridor will be like.
A raised intersection at Lovers Lane and Rugged Road. This was the project's first traffic-calming feature. As of May, the Town was collecting traffic data to see how well it works. The Town lists traffic calming as one of the project's goals, along with new drainage, better road cross-sections and paved surfaces.
A water main on Davkim Lane. A water main extension there was finished during the first season, which the Town says improves service access in the area.
A path through the State Forest. The Lovers Lane path leaves the road between Rugged Road and Old South Road and runs through DCR State Forest property. It is one of only two pieces of permanent infrastructure outside the public right-of-way. The other is an underground drainage system in a permanent easement on private land off Lovers Lane. Work restarted in the last week of August, and CC Construction began the season by laying gravel subbase for that forest section.
Trees and native shrubs. The more than 150 trees and 250 native shrubs going in along Lovers Lane this fall are meant "to bring back a natural look," according to the Town.
A project ten years in the making
This project has been in the Town's Capital Improvement Plan since 2016. Its funding came together over several Town Meetings:
- $1,000,000 in borrowing authorized at the 2016 Annual Town Meeting
- $1,000,000 from Real Estate Sales approved in 2017
- $534,800 in Free Cash approved in 2018
- $13,000,000 approved at the 2023 Annual Town Meeting for design and construction
- $6,472,673 in reappropriations and borrowings approved at the 2025 Annual Town Meeting
- $3,172,854 in MassDOT Chapter 90 funding
Easements were approved at the 2023 Special Town Meeting and are all recorded. The project went out to bid in March 2025, and bids were opened on April 23, 2025. In June 2025 the contract went to the lowest qualified bidder, CC Construction, with a total base bid of $18,799,759.58. Greenman-Pedersen, Inc. is the design and construction administration engineer, and Andrew Patnode, director of the Department of Public Works, coordinates for the Town.
In December 2025, a state grant changed the financing. The Inquirer and Mirror reported that a $4 million MassWorks grant reduces how much the Town needs to borrow and avoids an estimated $5 million in long-term debt service.
Following the closures this winter
Construction hours are Monday through Friday, 7 a.m. to 4 p.m. The Town expects full road closures throughout the project, and their locations shift as the contractor moves from one area to the next. Closures aren't posted on the project page. They appear in the Town's weekly Road Closures update, which you can subscribe to by email.
The notice for the week of November 9 closed Monohansett Road from Okorwaw Avenue to Evergreen Way from 7 a.m. to 4 p.m., Monday through Friday. Nancy Ann Lane to the Boulevard was closed during the same hours Tuesday through Thursday. The notice said detour signs would be posted on site and emergency access would be kept open unless otherwise noted.
Monohansett Road and Lovers Lane are scheduled to get their final pavement and berms first. Okorwaw's drainage, realignment and path come after that, once the utility lines are out of the way. Sometime between now and next summer, the gap between the Airport Road, Old South Road and Boulevarde paths is due to close. You can check the latest on the Surfside neighborhood page.
If a project like this is part of how you're thinking about your Surfside property, from road access to how close the new paths run to your lot, Jeremy Morgado is glad to walk through it with you street by street. Schedule a free consultation. Hablamos español.